• 2014 Technology Bond Package



     In November of 2014 voters passed a school bond for a total value of $102,545,000.  $17,650,000 was allocated to district technology upgrades which included infrastructure upgrades such as wireless internet enhancements, district phone system replacement and network operations improvements slated to begin June of 2015.

     

    Upgrade Timelines

    • Summer 2014       Network & phone assessments conducted
    • January 2015        Network & phone bid package released
    • February 2015      Network & phone bids received and vendors selected
    • February 2015      Vendor site walk and pre-design meetings
    • April 2015              Purchase orders issued for network & phone projects
    • Summer 2015       Daniel & Hardin cable replacement completed
    • June 2015             Network & phone replacement began
    • August 2015         Network & phone replacement completed
    • Fall 2016                Kennemer & Brandenburg cable replacement
    • September 2016   Classroom standard equipment installations completed

     

     

    Bond Presentations

     

  •  Bond Construction Web Site

     


    Network